Timeline
Project progress at a glance
A visual overview of the three phases of the project across the planned 30-month programme.
Overall programme time elapsed
This bar shows elapsed time across the full 30-month programme. A single colour fill shows only the time that has passed so far.
13%
↔ Scroll sideways to view the full timelineHover or click markers and bars for more detail
Holding Differently, Containing Distress
2025
2026
2027
2028
Project
Stages
Stages
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
Short Life
Working Group
Working Group
Project phases
Outputs &
reports
reports
Use the coloured bars or dots to jump to the related section below.
Phase 1
Phase 2
Phase 3
Phase 1 · Survey
Phase 2 · Appreciative Inquiry
Phase 3 · Resource creation & knowledge dissemination
Phase 1 · Survey
Online questionnaire design, recruitment, administration and analysis.
Phase completion
20%
What this phase covers
- Designing a survey with the workforce so it is meaningful, practical and easy to complete.
- Promoting participation across Scotland to build a wide picture of current practice and experience.
- Using the findings to identify patterns, strengths and areas for deeper exploration in later phases.
Milestones
Project start
1 Dec 2025 · completed
Questionnaire design and setup
15 Jan 2026 · upcoming / in progress
Survey live
1 Apr 2026 · upcoming / in progress
Survey analysis and dissemination
15 Aug 2026 · upcoming / in progress
Phase 2 · Appreciative Inquiry
Interview design, recruitment, fieldwork, transcription and analysis to understand successful restraint reduction in practice.
Phase completion
0%
What this phase covers
- Exploring what helps workers successfully avoid physical restraint and what conditions support good practice.
- Gathering detailed insight from services making progress towards restraint reduction.
- Producing early learning that feeds directly into practical resources and wider dissemination.
Milestones
Inquiry design begins
15 Oct 2026 · upcoming / in progress
Fieldwork starts
15 Jan 2027 · upcoming / in progress
Project mid-point findings
1 Feb 2027 · upcoming / in progress
Inquiry analysis completed
30 Jun 2027 · upcoming / in progress
Phase 3 · Resource creation & knowledge dissemination
Knowledge production, sense-making and development of resources, reports and wider dissemination activity.
Phase completion
0%
What this phase covers
- Turning the learning from the project into practical resources, reports and sector-facing outputs.
- Supporting sense-making and knowledge sharing so people can follow what has been learned and what is next.
- Making the final outputs easier to use in day-to-day practice and wider sector development.
Milestones
Resource planning
15 Oct 2027 · upcoming / in progress
Draft outputs shared
15 Feb 2028 · upcoming / in progress
Final resources published
31 May 2028 · upcoming / in progress
Milestone
· upcoming / in progress